Skip to content
Our Standards
Something not making sense? Ask us to decode it
Series Parts

Who can still say no to a data center

In some states a county can refuse a data center. In others the state holds the decision. The published counts of local pauses, bans and proposals run from 76 to 632, and each counts something different.

A hand-lettered sign reading NO NO NO DATA CENTER in the rear window of a white pickup truck parked on a residential street
The backlash is loudest at the local level, where the veto still works. Photo by Catboy69, CC BY 4.0, via Wikimedia Commons.

Credit: Catboy69, CC BY 4.0, via Wikimedia Commons

The Power Plant Next Door · Part 4 of nine. Start at the series hub. As of October 29, 2026.
Who can turn down a specific data center depends on where it is proposed. In Arizona a county board voted 4-1 on August 26 against rezoning land for one named project. In Texas counties have no zoning power; the governor ordered the state to pause data center permits, and what the pause covers is disputed. This part lays out four published counts of local pauses, bans and proposals, three national counts that run from 76 to 632 and one for New Jersey alone, each counting something different, then the ballot measures due on November 3, then who holds the decision in seven places.

How many places have said no depends on who is counting

Nobody keeps one official count of local data-center pauses and bans. The national counts run from 76 to 632 and a fourth covers New Jersey alone, because each one counts a different thing, so each is listed here with its date and what it includes.

Four published counts, and what each one counts
SourceCountWhat it countsAs of
National League of Cities tracker, as reported by Route FiftyAt least 76Cities, counties and towns that have “at least attempted” to adopt a moratorium or permanent ban, with the majority succeeding. The tracker is “by no means exhaustive.”August 28, 2026
GatherGov, on its own tracker page; credaily.com republished it on September 16632 (270 adopted)Of 1,030 jurisdictions with any moratorium activity in public meetings since January 2026, the 632 where GatherGov found “concrete action”: “a formal ordinance introduction by a councilmember, a staff study, an adopted ordinance, or an extension of a moratorium already on the books.” It is not a count of bans, and 172 more jurisdictions still at the stage of public requests are outside the 632. The page’s four categories (270 adopted, 25 extended, 120 introduced or at first reading, 232 under staff study or legal review) add to 647, not 632, and the page does not say how the two figures reconcile. It also reports 9 rejected, 5 repealed and 3 expired. GatherGov used an AI model to classify the meetings; credaily adds that GatherGov checked 30% of the dataset by hand.Published September 10, 2026 (data through early September)
Denver7 Investigates (Scripps News)“Nearly 500”, Denver7’s wordingTowns, cities and counties that have passed a moratorium or banned data centers, from Denver7’s own database. Moratoriums last from 90 days to five years in rare cases.October 7, 2026 (through September)
Gothamist93 in New JerseyNew Jersey towns that banned data centers through land-use rules, a count by climate activists. The article does not say how many are temporary.September 2, 2026

Of the National League of Cities entries, three are permanent bans: Marshall County, Indiana; Monterey Park, California; and St. Charles, Missouri. None of the four counts says how many projects were stopped, and the examples below show why a pause or a vote is not always a stop. The counts also do not nest. GatherGov’s 270 adopted actions sit below Denver7’s “nearly 500,” yet both are national counts: GatherGov counts formal action since January 2026, and Denver7 uses its own database. We could not line the two lists up against each other, so we do not add or reconcile them.

What local votes did to named projects
PlaceDateWhat happened
Pinal County, Arizona (Bisnow)August 26, 2026Supervisors voted 4-1 against rezoning more than 3,000 acres for the La Osa Energy Center, a plan by developer Vermaland for 11 data center buildings, a gas-fired power plant and battery storage. Bisnow reported that the vote “blocks the path to rezone.” It reported no response from the developer to the vote, and that the developer had said at a May hearing that it would reduce the site by 80%.
Palm Beach County, Florida (The Real Deal)Reported July 17, 2026Officials voted 5-1 to deny an amended zoning application for Project Tango, a 1 million-square-foot data center. The motion was “without prejudice,” so the developer can resubmit a similar proposal.
Hill County, Texas (Denver7)May (day not given)The county passed a one-year moratorium and rescinded it two weeks later, after a developer sued the county for $100 million.
Denver (Denver7)MayCity Council passed a one-year freeze. Denver7 reports that a 180,000 square-foot CoreSite data center had gone up across the street from Elyria Park, and that the moratorium has, for now, delayed two more buildings planned for the same site.
Guadalupe County, Texas (county minutes) (Part 7)April 21, 2026Commissioners voted 3-2 for the development agreement and then the tax abatement for the CloudBurst campus, with two commissioners voting no. Neither vote was a zoning decision, since the county has none.

Voters are also deciding some of these directly. Ballotpedia has at least 49 local data-center ballot measures in 13 states, 21 of them in Ohio, and 41 of them are on the November 3 ballot. As of October 28, six had been decided, and Ballotpedia says all six favored greater limits on development. One was in Port Washington, Wisconsin, where 66 percent (2,710 to 1,371) voted on April 7 to require voter approval for tax incremental districts above $10 million. The table below names each place, using Ballotpedia’s descriptions. By our reading of those one-line descriptions, 26 would ban, pause or add conditions, 8 ask whether to allow data centers, and 7 are zoning or agreement questions, so a vote on November 3 can cut either way.

The 41 local data-center measures on the November 3, 2026 ballot, by state and place
StateMeasuresPlaces and what each asks
California1Alhambra, Measure DB: ban data centers in the city.
Florida1Edgewater: bar new data centers from being approved, built, expanded or operated.
Illinois7Bloomington: advisory vote on a moratorium on large-scale data centers. Morgan County: advisory vote to restrict construction and operation. Joliet Township: advisory vote to approve AI data center construction. Chouteau, Granite City, Nameoki and Venice townships in Madison County: advisory votes to allow new data centers.
Kansas3El Dorado: ban high-impact data centers and certain battery storage. Emporia: ban high-impact data centers. Ottawa: ban data centers using more than 25 megawatts.
Maine4North Berwick: ban data centers of 25,000 square feet or more. Peru and Wells: 180-day moratoriums. Wiscasset: six-month moratorium on new or expanded applications.
North Dakota1Harwood: extra review before industrial developments, including data centers, are approved.
New Jersey1Downe Township: advisory vote to support data centers.
Nevada1Boulder City, Question 1: allow data centers in the Eldorado Valley Transfer Area.
Ohio21Bans: Conneaut, Defiance, Oregon and Sunbury (above 25 megawatts); Granville, Hubbard, Piqua, Upper Sandusky and Urbana (data center construction or data centers in the city); Pataskala and Trenton (large-scale data centers). Conditions: Grove City (voter approval for developments of 50 or more acres, 20 or more megawatts or 500,000 or more gallons of water a day); Perry (financial guarantees from hyperscale developers seeking tax incentives). Allow: Monroeville (advisory vote). Other: Ashville (uphold a term summary for talks with EdgeConneX on two data centers); Monroe and Sprigg townships in Adams County (zoning rules for unincorporated areas); Wilmington (four referendums on rezoning land to light industrial).
Wisconsin1Janesville: voter approval for development of the GM/JATCO site if costs exceed $450 million.

Your own county’s measure, if it has one, is on Ballotpedia’s page.

In Butte, Montana, a citizens’ group sued after local officials reversed course on a data-center initiative. The state Supreme Court allowed the initiative onto the ballot in an order the paper’s September 23 story says was filed “Tuesday,” which we infer was September 22 because the story gives no date, then vacated that order on September 24, saying it had not been told that ballots were already printed and mailed. The reports we found do not say whether the measure will appear on any ballot by another route.

Who can still say no
WHERE IT ZONES
Local (county and city). Where state law gives it zoning, a local vote can block a project: Pinal County, Arizona, did on August 26. In Texas, counties do not have zoning power.
STATE PAUSES
State. New York paused state environmental permits for data centers of 50 megawatts or more (Executive Order 62). Texas directed its environmental agency to pause data center permits until the ERCOT and Texas Water Development Board audits are complete; what the pause covers is disputed. Maine’s governor vetoed a statewide moratorium.
NOT YET
Federal. No moratorium has passed. Both Sanders-Ocasio-Cortez bills sit in committee. The Congressional Research Service says data center siting typically falls under state and local jurisdiction.
Where the power to stop a data center sits, October 29, 2026. Panel by HeadLines Decoded.

The state steps in

On July 14, 2026, New York became the first state to try the pause for itself. Gov. Kathy Hochul signed Executive Order 62. It directs one agency, the Department of Environmental Conservation, to hold discretionary permit applications for data centers that consume or can consume 50 megawatts or more, if the agency had not found the application complete before July 14. Facilities used mainly for manufacturing, research, education or medical care are excluded, and the order says it “does not apply to permits, approvals, licenses, or similar forms of permission from local governments.” The hold lasts until the Department of Public Service submits the final environmental impact statement. The order sets no end date, and the governor’s announcement says that study “will take up to a year” and that projects can then proceed “as long as they follow state, zoning code and other local approvals.”

The order also sets two 60-day tasks: Empire State Development is to post a Community Investment Framework, and the Department of Public Service is to form a Data Center Interconnection Working Group. On who pays for the wires, the order says the cost of electric system upgrades for large loads “should not be paid for by every-day New Yorkers.” The legislature had separately passed the Responsible Data Center Development Act (S10642/A11560), with a 20-megawatt threshold. As of August 3, Foley & Lardner reported that Hochul had not signed it, and on July 14 her office told Spectrum News she was “still looking at the legislation.” On August 27, State of Politics reported state Sen. Kristen Gonzalez urging her to sign it, and that Hochul has until the end of the year to act. We found no report after that of a signature or a veto, as of October 29.

Where Washington stands

Washington has produced bills and no statute. Sen. Bernie Sanders and Rep. Alexandria Ocasio-Cortez announced the Artificial Intelligence Data Center Moratorium Act on March 25, 2026. It would freeze AI data centers until national safeguards are in place. Sanders’ Senate bill, S.4214, was introduced March 25 and referred to the Commerce Committee. Ocasio-Cortez’s House bill, H.R.9442, was introduced June 24 and sent to the Energy and Commerce and Foreign Affairs Committees; LegiScan shows both still pending in committee. Rep. Frank Pallone, the ranking Democrat on Energy and Commerce, said at a June 24 subcommittee markup, “I am in favor of a national AI data center moratorium.”

A federal moratorium would need Congress to pass one of those bills. The Congressional Research Service, in a December 12, 2025 report on federal permit requirements for data center energy infrastructure, says individual data centers have “a discrete geographic footprint, typically falling under state and local siting jurisdiction,” though some federal approvals may still apply (PDF page 11). That report is about permits for the power side of a project. It does not map how far a federal override of a county could reach, and we found no bill that would give one.

Who can say no, place by place

The question “who can stop a data center” has a different answer in each of these seven places, as of the dates shown.

Who holds the decision in seven places
PlaceWho can say noSource and date
Arizona (Pinal County)The county board of supervisors, through the rezoning vote. It denied the La Osa rezoning 4-1.Bisnow, August 26, 2026
TexasNot the county on zoning: “Unlike a city, counties don’t have zoning capabilities,” said Darrek Ferrell of the Texas A&M Bush School. Counties vote on tax abatements and agreements. The state acts through agencies. On September 21 Gov. Greg Abbott directed the Texas Commission on Environmental Quality (TCEQ) to halt all permits sought by data centers until the ERCOT and Texas Water Development Board audits are complete (see the governor’s release and the Texas Tribune). TCEQ’s October 19 letter to the governor says it “has paused the issuance of all permits related to the construction or development of infrastructure directly supporting data centers,” is screening pending applications, and is suspending authorizations that need no permit “where possible.” The next day Inside Climate News reported that FracTracker and Public Citizen had counted 35 TCEQ permitting actions on data center projects since September 21; the governor’s office said no permits had been approved and that the pause covers approval, not processing. By October 22 TCEQ had taken its online filing system offline and suspended data center stormwater notices, the Texas Tribune reported. On August 3 Abbott also ordered ERCOT to deny grid connection to centers that fail an audit.KBTX, June 10, 2026; Governor’s release, September 21, 2026; Texas Tribune, September 21, 2026; TCEQ letter, October 19, 2026; Inside Climate News, October 20, 2026; Texas Tribune, October 22, 2026
New YorkThe state, for state environmental permits of 50 megawatts or more. Local permits are outside the order.Executive Order 62, July 14, 2026
PennsylvaniaNot a moratorium. Gov. Josh Shapiro’s August 18 order requires developers to show proof of local approvals before they can receive state permits, as Spotlight PA describes it, so the local decision comes first.Spotlight PA, August 2026
West VirginiaA 2025 law lets data centers in state-established districts “curtail local zoning ordinances and other regulatory processes,” and local governments have “little say or control over those districts,” reported West Virginia Watch. MultiState reads the law more broadly, as one that “prohibits localities from regulating or restricting data centers.”West Virginia Watch, April 30, 2025; MultiState, October 23, 2026
MaineThe legislature passed a statewide moratorium for data centers above 20 megawatts (LD 307), running to November 1, 2027, according to DatacenterDynamics. Gov. Janet Mills vetoed it in April 2026. In her veto letter, as DatacenterDynamics quotes it, she wrote that the final bill “fails to allow for a specific project in the Town of Jay that enjoys strong local support from its host community and region.” DatacenterDynamics describes that project as a $550 million redevelopment of the former Androscoggin Mill.MultiState, October 23, 2026; Brownstein Hyatt
New HampshireNo one yet. No statewide moratorium has passed. Gov. Kelly Ayotte has said she will propose one in the next biennial budget, expected to be finalized in summer 2027.NHPR, October 27, 2026

Three questions to put to the county clerk before a hearing follow from the table. Does the county zone this land, or only the city? Is the vote on a rezoning, a tax abatement or a development agreement, since each is a different decision? Which state permits does the project still need, and has the state paused any of them?

So the answer to who can stop a data center changes at the state line. A county holds the decision where state law gives it zoning, and does not where it lacks it. States are adding holds of their own on top, while West Virginia has gone the other way.

Correction, October 29, 2026: Earlier versions said more than 100 communities had used a pause or ban and about three dozen were outright bans, with no source for either; the story now gives four dated counts and what each includes. They also said the Montana Supreme Court had put the Butte initiative on the November ballot (it withdrew that order two days later); that the House bill was introduced in March (it was June 24); that Ballotpedia counted 38 measures in eight states with 20 in Ohio and 34 on November 3 (it now lists at least 49 in 13 states, 21 in Ohio and 41 on November 3); that New York’s order freezes every discretionary state permit a large data center needs (it holds only Department of Environmental Conservation applications not yet complete, does not reach local permits and exempts some facility types); and that a Congressional Research Service report mapped federal preemption (it is about federal permit requirements). Statements we could not source were removed: a 12-gigawatt New York queue figure, a Long Island quotation attributed to Hochul, a claim that decisions sit with the county in almost every state, and an advertising-spending figure. The first version also said New York was the only state to have stepped in; Texas and Pennsylvania had acted too, and are now in the table. New Hampshire is in the table as well, but no statewide moratorium has passed there; its governor has said she will propose one. This update gives Hill County and Denver the month Denver7 reports, describes Pinal County as a rezoning denial rather than a stop, attributes the Maine reason to the governor’s letter, changes the Texas row from “until state audits are done” to “until the ERCOT and Texas Water Development Board audits are complete,” and cuts the polling and presidential-post passages, which did not bear on where the decision sits. It also stops calling the 76-to-632 range a count of bans, since GatherGov’s 632 includes first readings and items under review and its own categories add to 661; names the places with November 3 measures; and adds the Maine bill’s threshold and end date, the New York bill’s latest status and the basis for the Butte date. Later on October 29: the GatherGov row now cites GatherGov’s own tracker page, published September 10 (credaily republished it September 16), with the page’s definition of the 632, the 1,030 jurisdictions it is drawn from, and the fact that its four categories add to 647; the 661 earlier in this note came from adding credaily’s rejected and repealed counts to those four. The Texas lines now report TCEQ’s October 19 letter, the October 20 dispute over 35 permitting actions and the October 22 suspensions, in place of a flat statement that Texas halted permits. The intro and count paragraph say that Gothamist’s 93 covers New Jersey alone.

Sources and further reading
HD
Written to standard
E.G. v4.18 · I.R.G. v1.14 · L.R.G. v1.9 · P.L.G. v1.10
Produced under the HeadLines Decoded Editorial, Image & Rights, Legal & Risk, and Production & Layout guidelines at the versions shown. What this means

See a mistake?

Editor written. AI used for spelling and grammar only.

More in Series Parts

Comments and questions

Keep it short. If we got something wrong, say so and show us where.